Two of Toscotec’s AHEAD-2.0M tissue machines started up at Vinda Personal Care (Guangdong) in Yangjiang, Guangdong, PRC. They will increase the group’s annual production by over 60,000 tons. With these start-ups, Vinda kicked off production at its new Yangjiang mill, strategically located by Yangjiang Port in south-west Guangdong.
Toscotec’s AHEAD-2.0M lines feature a second generation TT SYD-18FT of 5486mm diameter and state-of-the-art energy saving technology included in the profitable TT DOES package (Drying Optimization for Energy Savings). The two tissue machines started up on the same day at the same time, proving the high degree of proficiency of the start-up teams.
Throughout six years of close collaboration, Toscotec and Vinda have honed their synergy and consolidated their partnership. Toscotec’s Customer Care and Project Manager Stefano Raffaelli said, “Our teams have reached a very high efficiency of cooperation. Together we have optimized the project timing, during both installation and commissioning. We cut down the duration of tests at the mill, thanks to the thorough checks we perform during pre-assembly at our factory, as an integral part of our quality guarantee”.
Vinda International’s Project Development Center Director, Mr. Liang Weixiong commented, “After three months of intensive work on site, it is a great satisfaction to see these start-ups hit the targets of the scheduled date and time. It is indeed the result of very careful preparation on all the machine’s functions”.
Stefano Raffaelli added, “For all our Vinda’s machines we implemented an efficient use of steam and condensate with different levels of energy recovery. This carefully balanced system ensures the lowest possible energy consumptions. The dedication and competence of the Vinda and Toscotec teams bring out the best of our technology. We achieved good results in terms of energy usage, as well as production increase with speed-ups and optimizations, all of which exceed the original objectives of the projects”.
Toscotec’s tissue lines are currently running at six of Vinda’s production bases across China, in Shandong, Hubei, Sichuan, Zhejiang and Guangdong.
In the coming months, Vinda will fire up another four Toscotec’s lines at its new paper mill in Xiaogan, Hubei province.